General Meeting Agenda - January 6, 1999
Minutes are in italics.
Announcements
-
Fill out meeting schedule
-
Opal EM done by Feb 1.
CDR immediately following around the 3rd. Flight done on March 1 to do
environmental testing. Opal complete on April 1 to do final ops testing.
-
Lab cleanup
Subsystem Discussion
-
General
-
Any word on darpa money?.
Twiggs will send email to find out
-
Inhouse prototyping of boards.
Thurs 1pm in 007
-
System Integration
-
Need several system engineers
to work on ops, testing, and integrating Opal
-
Still work to do on OGIWED.
Friday at 11am Ogiwed meeting
-
Harnesses and integration testing.
-
Accelerometers / Magnetometer
-
Update. Working
on board design
-
Communications
-
Update. Monday meeting
at 5:30 with mentors.
-
CPU
-
Get Opal up and running
-
Use EEPROMS
-
make watchdog power cycle cpu/tnc
-
Launch Interface
-
No news. Jawsat to
return mass model by end of January
-
Picosatellite Launcher
-
Pro E license, Prof Twiggs.
He will check into this
-
Plan of attack. Testing!
David and Jeff to meet to discuss this
-
Launcher instrumentation.
Box size
-
NEAs and actuators.
-
News from Aerospace?
-
Artemis talking to NEA needs
info. Jeff will work on this, have by Friday.
-
Power
-
Update.
-
Any news from Lockheed?
-
Woody Allen working off batteries,
getting flight ready
-
Sun simulator
-
Structure
-
No News Returned end of january
-
Testing
-
Update.
-
Identify testing needs
-
JAWSAT
-
Ops
|