Mech Team Schedule
Aug 22 launcher prototype
Sept
test prototype
Oct 5
launcher EM fab
Nov 5
structure shake
Nov 13 deliver
launcher EM
Nov
Vibe test
Nov 30 OPAL mass model
Jan 1
flight launcher fab
Feb 1
finish flight launcher
Mar
flight environ testing
May 1 OPAL flight
delivery
Sep 1
Launch at VAFB
|
|
OPAL
Mechanisms Team Meeting Agenda
November 2, 1998
Announcements
Subsystem Discussion
Picosat Launcher
Engineering Model -- Jeff
-
Order rect. and Belleville springs,
latch cables -- rectangular springs have been ordered, but it will be
5 weeks to delivery; Jeff to order Belleville springs; Andy ordered
cables and suager -- to be delivered by Friday
-
Fabrication quote and production
-- delivery Nov. 13
-
In-house part fabrication --
Jeff to get part list to Santiago
-
Dry lube application -- requires
$95 min. order, has a 2-day turn around, just need to bring parts in and
drop them off when ready
-
Instrumentation -- Eric coordinated
with Sean re: OGIWED and launcher connections and pin assignments, still
need to nail down assignments
Hall effect sensors not working -- located documentation, try this week
to get them to work
-
Picosat mass models -- Jamie
to call Aerospace, talk to mentors and SCU to find out details on their
mass models
Launch Interface -- David
-
Actuator redesign and method
of attaching OPAL -- meeting scheduled for Tues. at 2:30 pm to discuss
interface issues and options
Need to talk to NEA and ask about ability to receive 28V signal to actuator
and ability to rotate bolt while tightening it down
-
Part fabrication
-
Structural analysis
-
Production drawings
Structure -- Santiago
-- not at the meeting
-
Machining coordination
-
Shake structure
-
Static loads test
-
Flight structure:
-
Parts to send to WSU for mass
model
Testing -- David and Andy
-
Interface, OPAL structure, and
launcher EM verification testing -- Mike McMann called and
said that Nov. test won't work. He estimates 5-day requirement to
complete tests. David to call him and ask what can be done to decrease
that time. David to tell them we are willing to be "on call," help
with the setup and testing, and split up the testing time if necessary.
Jamie to talk to Twiggs about re-establishing contact to ensure that we
get the testing that has been promised.
-
Testing procedures -- David
to fax it to LM for verification
JAWSAT and Orbital Sciences
Corp. -- Jeff
-
Interface Control Document update
-- need to add to ICD and send to WSU
-
JAWSAT CDR & PIWG Oct. 29
at Weber St. -- OPAL action item summary posted here,
full minutes to be posted after they are completed by OSSS
-
OPAL mass model Nov. 30 --
we will likely receive it back by Jan 1 since their shake test is set for
12/7 and they are done with the mass model after that
-
Battery trickle charger through
ASU -- Carlos GS to coordinate with ASU
Miscellaneous
-
Schedule updates --
need to update overall OPAL schedule and include margin
|