Mech Team Schedule 

Aug 22  launcher prototype    
Sept      test prototype   
Oct 5     launcher EM fab    
Nov 5     structure shake   
Nov 13   deliver launcher EM   
Nov        Vibe test   
Nov 30  OPAL mass model    
Jan 1     flight launcher fab   
Feb 1    finish flight launcher   
Mar       flight environ testing   
May 1   OPAL flight delivery   
Sep 1    Launch at VAFB   
 

OPAL Mechanisms Team Meeting Agenda          November 23, 1998 
 

Subsystem Discussion 

    Picosat Launcher Engineering Model -- Jeff 
    • Assembly complete
    • Design issues
    • Design review on Dec. 9th
    • Instrumentation -- Eric to install next week
    • Picosat mass models -- all delivered
    • Need to start thinking about how to conduct functional testing
    Launch Interface -- David 
    • Assembly complete 
    • Production drawings  -- Jeff to update drawings
    Structure -- Santiago   
    • Machining coordination 
    • Shake structure assembly complete
    • Static loads test -- possibility of conducting it bolted horizontal with a horizontal load
    • Flight structure
    Testing -- David and Andy 
    • Interface, OPAL structure, and launcher EM  verification testing at Ames tomorrow -- badge list: Santiago, Jeff, David, Andy, Eric, Bryan.  Meet at 8 am at Ames for testing.  Contact is Howard Menche at 604-6048 in bldg. 244-N
    • Testing procedures -- took them over to Ames this morning
    JAWSAT and Orbital Sciences Corp. -- Jeff 
    • Interface Control Document by 11/30 
    • PIWG Dec. 2 at VAFB
    • OPAL mass model to OSSS Nov. 30 -- Andy to mail it on Wed.
      • Weber State University 
        Center for Aerospace Technology 
        1805 University Circle 
        Ogden UT 84408-1805
    • Battery trickle charger through ASU