Mech Team Schedule
Aug 22 launcher prototype
Sept
test prototype
Oct 5
launcher EM fab
Nov 5
structure shake
Nov 13 deliver
launcher EM
Nov
Vibe test
Nov 30 OPAL mass model
Jan 1
flight launcher fab
Feb 1
finish flight launcher
Mar
flight environ testing
May 1 OPAL flight
delivery
Sep 1
Launch at VAFB
|
|
OPAL
Mechanisms Team Meeting Agenda
November 23, 1998
Subsystem Discussion
Picosat Launcher Engineering
Model -- Jeff
-
Assembly complete
-
Design issues
-
Design review on Dec. 9th
-
Instrumentation -- Eric to
install next week
-
Picosat mass models -- all
delivered
-
Need to start thinking about
how to conduct functional testing
Launch Interface -- David
-
Assembly complete
-
Production drawings
-- Jeff to update drawings
Structure -- Santiago
-
Machining coordination
-
Shake structure assembly complete
-
Static loads test -- possibility
of conducting it bolted horizontal with a horizontal load
-
Flight structure
Testing -- David and Andy
-
Interface, OPAL structure, and
launcher EM verification testing at Ames tomorrow -- badge list:
Santiago, Jeff, David, Andy, Eric, Bryan. Meet at 8 am at Ames for
testing. Contact is Howard Menche at 604-6048 in bldg. 244-N
-
Testing procedures -- took
them over to Ames this morning
JAWSAT and Orbital Sciences
Corp. -- Jeff
-
Interface Control Document by
11/30
-
PIWG Dec. 2 at VAFB
-
OPAL mass model to OSSS Nov.
30 -- Andy to mail it on Wed.
Weber State University
Center for Aerospace Technology
1805 University Circle
Ogden UT 84408-1805
-
Battery trickle charger through
ASU
|