Mech Team Schedule
Aug 22 launcher prototype
Sept
test prototype
Oct 5
launcher EM fab
Nov 5
structure shake
Nov 13 deliver
launcher EM
Nov
Vibe test
Nov 30 OPAL mass model
Jan 1
flight launcher fab
Feb 1
finish flight launcher
Mar
flight environ testing
May 1 OPAL flight
delivery
Sep 1
Launch at VAFB
|
|
OPAL
Mechanisms Team Meeting Agenda
November 30, 1998
Subsystem Discussion
Picosat Launcher Engineering
Model -- Jeff
-
Design issues
4 tubes
-
Design review on Dec. 9th --
need to get word out
-
Instrumentation -- Eric, Santiago
to install -- software being worked on in the next few weeks as well.
-
Functional testing -- Andy
and Scott to come up with drafts for test procedure
-
Flight model modifications and
drawings
-
Order new actuators and get
old ones refurbished -- Andy to check on this
-
Jeff to check with Carolyn
on status of rect. springs
Launch Interface -- David
-
Production drawings
-
WSU to match drill holes in
feet
Structure -- Santiago
-
Shake structure assembly complete
-
Static loads test -- possibility
of conducting it bolted horizontal with a horizontal loadI -- have shock
test take the place of the static loads test
-
Flight structure
Testing -- David and Andy
-
Test summary
-
Test results to be posted on
web -- David to scan in results from test
-
Shock test at Ames
-
Necessity of cantilevered test
-- not accurate, wouldn't result in much helpful data
JAWSAT and Orbital Sciences
Corp. -- Jeff
-
Interface Control Document by
11/30 -- post to web
-
PIWG Dec. 2 at VAFB
-
OPAL mass model shipped to OSSS
Nov. 30
|