Mech Team Schedule  

Aug 22  launcher prototype     
Sept      test prototype    
Oct 5     launcher EM fab     
Nov 5     structure shake    
Nov 13   deliver launcher EM    
Nov        Vibe test    
Nov 30  OPAL mass model     
Jan 1     flight launcher fab    
Feb 1    finish flight launcher    
Mar       flight environ testing    
May 1   OPAL flight delivery    
Sep 1    Launch at VAFB    
 

OPAL Mechanisms Team Meeting Agenda          November 30, 1998 
 

Subsystem Discussion 

    Picosat Launcher Engineering Model -- Jeff 
    • Design issues

    • 4 tubes
    • Design review on Dec. 9th -- need to get word out
    • Instrumentation -- Eric, Santiago to install -- software being worked on in the next few weeks as well.
    • Functional testing -- Andy and Scott to come up with drafts for test procedure
    • Flight model modifications and drawings
    • Order new actuators and get old ones refurbished -- Andy to check on this
    • Jeff to check with Carolyn on status of rect. springs
    Launch Interface -- David 
    • Production drawings 
    • WSU to match drill holes in feet
    Structure -- Santiago     
    • Shake structure assembly complete
    • Static loads test -- possibility of conducting it bolted horizontal with a horizontal loadI -- have shock test take the place of the static loads test
    • Flight structure
    Testing -- David and Andy 
    • Test summary
    • Test results to be posted on web -- David to scan in results from test
    • Shock test at Ames
    • Necessity of cantilevered test -- not accurate, wouldn't result in much helpful data
    JAWSAT and Orbital Sciences Corp. -- Jeff 
    • Interface Control Document by 11/30 -- post to web
    • PIWG Dec. 2 at VAFB
    • OPAL mass model shipped to OSSS Nov. 30