Mech Team Schedule
Aug 22 launcher prototype
Sept
test prototype
Oct 5
launcher EM fab
Nov 5
structure shake
Nov 13 deliver
launcher EM
Nov
Vibe test
Nov 30 OPAL mass model
Jan 1
flight launcher fab
Feb 1
finish flight launcher
Mar
flight environ testing
May 1 OPAL flight
delivery
Sep 1
Launch at VAFB
|
|
OPAL
Mechanisms Team Meeting Agenda
December 7, 1998
Subsystem Discussion
Picosat Launcher Engineering
Model -- Jeff
-
Design issues
-
Design review in January
-- combined with OPAL CDR with a main purpose to review testing.
Have mentors, Colin Francis review test procedure before then
-
Instrumentation -- Eric to
finish installing
-
Functional testing -- decided
that we should try to get into Ames the second week of January to do a
repetitive functional shake test and thermal cycling
-
Flight model modifications and
drawingsI -- Jeff to work on next week
-
Order new actuators and get
old ones refurbished -- Andy contacted NEA, they are sending a new quote
for $2000 a piece. We may want to use the two we already have for
flight to save $4000
Launch Interface -- David
-
Production drawings -- Jeff
to work on next week
-
WSU to match drill holes in
feet
Structure -- Santiago
-
Shake structure assembly complete
-
Static loads test -- possibility
of conducting it bolted horizontal with a horizontal load -- better
to get in and do shock test at Ames
-
Flight structure
Testing -- David and Andy
-
Test summary
-
Test results to be posted on
web -- David to scan results, Jeff to post on web
-
Shock test at Ames -- need
to look into this when we get the mass model back
JAWSAT and Orbital Sciences
Corp. -- Jeff
-
Interface Control Document by
11/30 -- post to web
-
PIWG Dec. 2 at VAFB
-
OPAL mass model shipped to OSSS
Nov. 30
|