Payload Integration Working Group Weekly Telecon Notes
October 23, 1998 

Vandenberg

  • Payloaders need to provide list of what will be needed at Vandenberg, i.e., office equipment, office space, etc.
  • PIWG scheduld for Dec. 2nd at Vandenberg to tour facilities 


JAWSAT CDR

  • CDR scheduled for October 29th, to finish on morning of 30th with PIWG that afternoon at Radisson Hotel in Ogden, UT
  • Payloaders to present schedule, status, and issues at each PIWG.  Schedule to include milestones and critical path items with all top-level milestones
  • Payloaders to post schedules on CAST ftp site
General
  • JAWSAT isogrid will have different hole spacing for EM and flight versions
    CAST to revise and send out drawings and template for hole placement
    Gary Shirey responsible to complete
  • Need to deliver mass models to Weber by 11/30
  • Mass model might have to be deployable if it flies, depending on how late decision is made to fly mass model
  • No real-time control on OSC fourth stage -- all pre-programmed