Payload
Integration Working Group Weekly Telecon Notes
October 23, 1998
Vandenberg
-
Payloaders need to provide list
of what will be needed at Vandenberg, i.e., office equipment, office space,
etc.
-
PIWG scheduld for Dec. 2nd at
Vandenberg to tour facilities
JAWSAT CDR
-
CDR scheduled for October 29th,
to finish on morning of 30th with PIWG that afternoon at Radisson Hotel
in Ogden, UT
-
Payloaders to present schedule,
status, and issues at each PIWG. Schedule to include milestones and
critical path items with all top-level milestones
-
Payloaders to post schedules
on CAST ftp site
General
-
JAWSAT isogrid will have different
hole spacing for EM and flight versions
CAST to revise and send out drawings and template for hole placement
Gary Shirey responsible to complete
-
Need to deliver mass models
to Weber by 11/30
-
Mass model might have to be
deployable if it flies, depending on how late decision is made to fly mass
model
-
No real-time control on OSC
fourth stage -- all pre-programmed
|